A and B can do a work in 12 days, B and C in 15 days and C and A in 20 days. If A, B and C work together, they will complete the work in :
(1) 5 days
(2) \(7 \frac{5}{6}\) days
(3) 10 days
(4) \(15 \frac{2}{3}\) days
Adv.
A and B can do a piece of work in 72 days. B and C can do it in 120 days, A and C can do it in 90 days. In how many days all the three together can do the work ?
(1) 80 days
(2) 100 days
(3) 60 days
(4) 150 days
A particular job can be completed by a team of 10 men in 12 days. The same job can be completed by a team of 10 women in 6 days. How many days are needed to complete the job if the two teams work together?
(1) 4 days
(2) 6 days
(3) 9 days
(4) 18 days
A can do a work in 6 days and B in 9 days. How many days will both take together to complete the work?
(1) 7.5 days
(2) 5.4 days
(3) 3.6 days
(4) 3 days
A and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. C alone can do the work in :
(1) 60 days
(2) 120 days
(3) 80 days
(4) 30 days